Processus de construction abrégé

Temps de séchage : 5 jours

Processus de construction abrégé
Temps de séchage : 5 jours

Allow the concrete slab to harden for 2 days. Then grind the slab smooth, removing the concrete skin which “opens” the concrete and allows the slab to dry faster.

Once the grinding is finished, construction work can continue. As the slab is smooth from the grinding, no self-levelling compound is required. However, it must be watered and covered with plastic to avoid shrinkage cracks.

Option

Allow the concrete slab to harden while watering it under plastic for 7 days. Then grinding can commence and no more watering is required.

Avantages

Pros Temps de construction nettement plus court
Pros Coûts plus bas
Pros Moins de façonnage des bords
Pros Moins de risques
Pros Processus de construction dans le respect de l’environnement

L’importance d’une coulage de qualité

La qualité de surface de la dalle en béton issue du coulage et la taille de la ponceuse déterminent la vitesse à laquelle la dalle en béton peut être terminée.

Exemple – ponçage avec une HTC 950 RX

Du béton coulé de classe A, présentant +/- 3 mm sous une règle de 2 m, d’arête droite = environ 40 m² par heure
Du béton coulé de classe B, présentant +/- 5 mm sous une règle de 2 m, d’arête droite = environ 20 m² par heure